Do not judge waterproofing only by its colour. Before tiling, check that leaks and weak plaster are repaired, corners and pipe entries are sealed as part of one named system, the coating or membrane is complete and cured, and the planned water-holding check passes. Also check that water can still fall towards the drain.
1. Fix the water source first
A wet mark does not always sit below the real leak. Water can move along a pipe, joint or slab. Ask the team to check supply pipes, drain connections and the old base before applying a new waterproof layer.
Repair loose plaster, cracks or broken areas first. Waterproofing needs a suitable base. A new grey or blue coat over dust and weak material is not a finished repair plan.
In a flat in Sargasan, Raysan or GIFT City, ask the building team before work touches a shared pipe shaft or common line. In an older Gandhinagar sector home, ask what old repairs were found when the floor was opened. The address does not prove the cause; the site check does.
Further reading: Sika India: SikaTop 561 Seal for under-tile wet-room waterproofing · Sika India: SikaTop 107 Seal IN application and curing
2. Name the whole system
Ask for the product name, the base it is going on, the number of layers and the current maker instructions. A liquid coating, cement-based coating and sheet membrane do not all use the same preparation or waiting time.
Ask who mixes and applies it, and how the team will check coverage. Do not accept extra water, random cement or a second product mixed in unless the written system allows it.
Keep a photo of the sealed pack and batch details. This does not prove good work, but it helps you check that the agreed material was used.
This article does not recommend one brand. The selected product and all supporting materials must be suitable for the actual base and wet area.
Further reading: Sika India: SikaTop 561 Seal for under-tile wet-room waterproofing · Sika India: SikaTop 107 Seal IN application and curing · MAPEI India: bathroom waterproofing and ceramic-tile system
3. Look closely at corners, drains and pipe entries
The wall-to-floor joint, inside corners, drain edge and places where pipes pass through the surface need a clear detail. These points can move or crack differently from a flat area.
Ask which tape, fabric, collar, sealant or formed piece belongs with the chosen system. Sika’s wet-room documents, for example, call out floor-to-wall joints, corners, drains and pipe entries as separate details. Use the instructions for the system on your site.
Take photos before the next layer hides these places. Check that fittings are in their final positions. Cutting a new hole later can break the waterproof layer.
Further reading: Sika India: SealTape F for corners, floor-to-wall joints and pipe entries · MAPEI India: bathroom waterproofing and ceramic-tile system

4. Let it cure, then do the agreed water check
Cure means giving the material the time and conditions it needs to become ready. The time differs by product, temperature and the next step. Ask the team to write down when the final layer was applied and when testing may start.
Do not fill the floor with water too early. One current Sika cement-based system says it must not face ponding before seven days. That is an example of why the actual product sheet matters, not a shortcut copied from another bathroom.
For a water-holding check, agree how the drain will be closed, where the water level will be marked, how long it will stay, and which nearby or lower areas will be checked. Allow for evaporation when reading a small level change. Record the start and end with photos. If the level drops or damp appears, stop and investigate before tiling.
Further reading: Sika India: SikaTop 107 Seal IN application and curing

5. Check where water will go after the test
After the check, release the water and watch its path. The floor needs a gentle fall towards the drain. Ask the team to show how the tile and adhesive will keep that fall.
Check the drain cover, bathroom door, threshold and finished floor height together. A good membrane does not fix a floor that sends water away from the drain or leaves a risky step at the door.
Do this before buying all the tiles. Tile size and drain position can affect how neatly the finished floor can be shaped.
6. Keep a small handover record
Keep the product sheet, batch photo, dates, hidden-work photos and test result with your renovation papers. Note who checked the pipes and who checked the waterproofing.
Ask what protection will cover the finished waterproof layer while tiles are installed. Tools, sharp edges and later drilling can damage work that already passed.
The free guide below gives you a phone-friendly site record, two worked examples and questions to use before the tiles go down. If you want local help, share the filled notes with the team assessing your bathroom.
YOUR FREE TAKE-HOME GUIDE
Check the hidden work before tiles cover it.
8 pages · PDF · 382 KB
An eight-page bathroom waterproofing site-check guide with two examples, a water-test record and a simple handover sheet.
No sign-up needed. Save it or share it with your family.
Sources & useful reading
Checked on 21 October 2026. Shop prices, stock and product terms can change.
- Sika India: SikaTop 561 Seal for under-tile wet-room waterproofing
Manufacturer data sheet for suitable wet-area uses and substrates. Follow the current sheet for the product selected on site.
- Sika India: SealTape F for corners, floor-to-wall joints and pipe entries
Manufacturer detail guidance. Use compatible parts from the chosen system.
- Sika India: SikaTop 107 Seal IN application and curing
Manufacturer example for base preparation, layers, pipe detailing and product-specific curing. It is not a universal timing rule.
- MAPEI India: bathroom waterproofing and ceramic-tile system
Manufacturer system view showing preparation, waterproofing, drain, tape, adhesive, tile, grout and sealant as connected parts.